09 May 2009

Top Garden Wall continued

Work on the wall has progressed, albeit somewhat erratically. The May Bank Holiday, some bad weather, a collapsed drain and some plastering have all interrupted work, however the next week should see the completion. The main part is complete now, with just the short stretch below the new gate and above the rockery to be finished.

I should explain that the collapsed drain was not ours. It occurred on a Static Caravan Park in Newquay and Chris went off to do a couple of days digging and fixing. The plastering was a job that Chris knew about before he started here; it was just a case of finding a suitable time to do it.

End of Day 4 - New Gate Entrance

End of Day 5 - Field Side

End of Day 5 - Garden Side

End of Day 6 - Garden Side

End of Day 7 - Garden Side

End of Day 8 - Garden Side

End of Day 9 - Rockery

No comments: